MIL-PRF-914C
4.6.5.2 Subgroup 1. A sample of 13 parts shall be randomly selected. If one or more defects are found, the lot
shall be rescreened and defects removed. A new sample of 13 parts shall be randomly selected. If one or more
defects are found in this second sample, the inspection lot shall be rejected and shall not be supplied to this
specification.
4.6.5.3 Subgroup 2. A sample of 13 parts shall be randomly selected. If one or more defects are found, the lot
shall be rescreened and defects removed. A new sample of 13 parts shall be randomly selected. If one or more
defects are found in this second sample, the inspection lot shall be rejected and shall not be supplied to this
specification.
4.6.5.4 Subgroup 3. A sample of eight parts shall be randomly selected. If one or more defects are found, the lot
shall be rescreened and defects removed. A new sample of eight parts shall be randomly selected. If one or more
defects are found in this second sample, the inspection lot shall be rejected and shall not be supplied to this
specification.
4.6.5.5 Disposition of sample units. Sample units which have passed all the group B, subgroup 1 and subgroup 2
inspections, method A mounted networks only, may be delivered on the acquisition document provided they are
within resistance tolerance and meet requirements for visual and mechanical inspection. Sample units which have
been subjected to subgroup 3 inspections shall not be supplied to this specification.
TABLE XVI. Group B inspection (ER only).
Requirement
Test method
Sample
Number of
Inspection
paragraph
paragraph
size
defects allowed
Subgroup 1 1/
Visual and mechanical examination
0
13
(when applicable)
Subgroup 2 2/
Resistance-temperature characteristic
13
0
Subgroup 3 2/
8
0
Resistance to solvents
1/
Only applicable when marking inspection is not performed in group A inspection. No defects shall be
permitted. Marking shall remain legible at the end of all tests.
2/
If the manufacturer can demonstrate that this test has been performed five consecutive times with zero
failures, the frequency of this test, with the approval of the qualifying activity, can be performed on an annual
basis. If the design, material, construction, or processing of the part is changed, or if there are any quality
problems or failures, the qualifying activity may require resumption of the original test frequency.
4.7 Periodic group C inspection (ER only). Periodic inspection shall consist of group C inspection tests specified in
table XVII, in the order shown. They shall be performed on sample units selected from lots that have passed group A
and group B inspection. Except where the results of these inspections show noncompliance with the applicable
requirements (see 4.7.6), delivery of products which have passed group A and group B inspections shall not be
delayed pending the results of these periodic inspections.